How to compare Sydney duplex build quotes
Two duplex quotes are comparable when they price the same design, site information and scope. Ask each builder to identify what was included, what was allowed for and what still depends on further information before comparing the total.
Give each builder the same package
Send the same drawing revision, survey and specification. If some details are still being designed, list them so each builder can state the assumptions behind their number. Keep the quote date and drawing revision beside every total. When a drawing changes, ask which items need repricing.
Put the main differences on one page
Use a simple comparison sheet and record the figure and any qualifications each builder gives you. An empty row is a question to resolve.
- Site works. What is included for demolition, excavation, access, disposal and retaining? What assumptions have you made about the ground?
- Services. What work for incoming services, drainage or other utilities is included? Who is responsible for any later connections?
- Interior inclusions. Which items are fixed, and what allowances have you carried for kitchens, joinery, tiling and fixtures in both homes?
- External works. Are driveways, fences, landscaping and usable outdoor areas part of this price?
- Timing and exclusions. Which inspections, permits or consultant items sit outside the price? What could affect the commencement date or programme?
Compare what a display home shows with what the quote includes
A display home or project image can help you decide which finishes and details you want. Ask whether the façade, glazing, ceiling heights, appliances, joinery and landscaping you are looking at are part of the price you were given. Keep a photo or specification reference beside any item you want included.
Resolve the large unknowns while the design can still change
Ask which assumptions have the biggest potential effect on the price. If access, excavation or structure is unclear, get those questions in front of the right consultant before comparing optional finishes. If the quotes are still beyond the budget once the scope lines up, review the layout, structure and specification together so the changes preserve the parts of the design that matter most. Construction cost per square metre · Value engineering and cost review