NAVIGATING TIMEFRAMES: From Design to Approval

2 min readFernando Banales

Hand-drawn pencil sketch of a long, low timber-clad house set into a coastal landscape, with a ramp and native planting

One of the most common questions we hear is, “How long does it take to go from design to approval?” While the answer depends on several factors, understanding the key stages can help you plan your project with confidence. Let’s walk through the process and typical timeframes involved.

Starting Your Project: Briefing & Site Analysis

The first step is ensuring we're aligned on your vision and goals. This stage includes:

Why This Matters: Taking time here allows us to identify and address potential challenges early. Projects that invest in a thorough brief and site analysis typically get the concept right from the start.

Putting Pen to Paper: Concept Design & Application Drawings

With the foundation set, the next stage is to develop the design concept. Here we:

Once the design is finalised, we prepare the necessary application drawings relative to the application type being sought (next section).

Pictured- Concept Render of Kitchen for a Bellevue Hill Renovation (Construction 2025)

The application process plays a big role in determining how long approval takes. There are two main paths:

Stage 1

Stage 2

Timeframe: This process typically spans 12-18 months, depending on council responsiveness and project complexity. Factor in some flexibility for unexpected delays like extended council reviews.

This path is quicker and more straightforward:

Timeframe: The entire process can take 5-6 months, with final approval and tender-ready drawings included. This streamlined approach saves time and cost, making it ideal for many projects.

The Bigger Picture

Understanding the application options is key to managing your project’s timeline. The Development Application process can take 12-18 months, while the Complying Development process typically takes 5-6 months.

To keep your project on track:

Every project is unique, but with the right planning and expertise, the journey from design to approval can be smooth and successful.